Theme 2 · Edexcel GCSE (9–1) Business, spec 1BS0

2.3.2 Working with suppliers

Free notes on working with suppliers, the terms the examiner expects you to use, and a worked question with the answer explained. This is one numbered section of the Pearson specification — part of 2.3 Making operational decisions.

What 2.3.2 covers

Managing stock: interpretation of bar gate stock graphs, the use of just-in-time (JIT) stock control. The role of procurement: relationships with suppliers (quality, delivery — cost, speed, reliability — availability, cost, trust); the impact of logistics and supply decisions on costs, reputation and customer satisfaction.

Key terms for 2.3.2

Definitions in the wording the mark scheme rewards — short enough to learn, exact enough to score.

Quality control
A system of checking finished products at the end — faults are found late, causing wastage.
Buffer stock
A minimum stock level held at all times, in case a supplier fails to deliver on time.
Procurement
Obtaining the right supplies from the right supplier — reliability, quality and delivery matter more than the lowest price.
Quality assurance
Building quality into every stage of production — every member of staff has quality responsibilities.
Total Quality Management (TQM)
A culture in which every employee takes responsibility for quality.

2.3.2 worked example

One question from the bank, exactly as a student sees it — with the answer and the explanation that follows a submission.

Question 12.3 · 2.3.21 mark

What is the name for the extra stock a business keeps in reserve, in case a delivery arrives late or demand suddenly rises?

Show the answer and explanation

Answer: buffer stock

Buffer stock is a reserve kept above the normal amount of stock on hand, protecting the business if a delivery is late or demand jumps. The cost is cash tied up, storage space, and the risk of damage or goods going out of date.

Set 2.3.2 homework that marks itself

Every question in the bank is tagged to its sub-topic, so you can set work on 2.3.2 alone. Students get instant marking and an explanation; you get the class breakdown.

Back to 2.3 Making operational decisions or all sub-topics.