What 2.3 covers

2.3 questions and answers — free worked examples

Two questions on 2.3, exactly as they appear in the bank, with the answer and the explanation a student would see after submitting.

Question 12.3 · 2.3.11 mark

A bakery makes a single wedding cake to the customer’s own design, with hand-modelled sugar flowers and a personalised inscription. Which production method is this?

  1. ABatch production
  2. BJob production
  3. CFlow production
  4. DJust-in-time production
Show the answer and explanation

Answer: Job production

Job production makes one-off items to the customer’s specification. It needs skilled workers and takes longer, so the cost per unit is high — but the customer pays a high price for a unique product.

Question 22.3 · 2.3.11 mark

A bakery makes 300 white loaves, then stops, cleans the mixers and re-sets the machines before making 300 wholemeal loaves. What production method is this?

  1. AJob production
  2. BBatch production
  3. CFlow (line) production
  4. DOne-off production
Show the answer and explanation

Answer: Batch production

Batch production makes identical items in groups, with a changeover (cleaning or re-setting machines) between each batch. It is more flexible than flow production but less productive, because production stops between batches.

Set 2.3 homework that marks itself